Timeline of Events

09/05/2014 - Signed Land Contract

28/06/2014 - Signed PWC to build St Tropez 28 with Boutique Homes

11/12/2014 - Colours appointment; discovered forged signatures

21/12/2014 - Signed Quotation to build Essex 27 with Porter Davis Homes

06/01/2015 - Cancelled PWC with Boutique Homes

06/01/2015 - Finalised quotation with Porter Davis Homes – File sent to Head Office

02/03/2015 - World of Style appointment with Porter Davis Homes

11/03/2015 - Land Titles issued

23/03/2015 - Tender appointment with Porter Davis Homes; site works a staggering $40k ($15k above what was originally quoted)

25/03/2015 - Land Settlement

28/03/2015 - Re-signed PWC to build St Tropez with Boutique Homes

30/03/2015 - Cancelled build with Porter Davis Homes

30/04/2015 - Pre-approval from Westpac received

08/05/2015 - Contract signing and electrical appointment with Boutique Homes

19/05/2015 - Westpac undervalued house/land by $34k

01/06/2015 - Colours selection

10/06/2015 - Build Over Easement (BOE) application submitted to South East Water

17/06/2015 - Developers Approval submitted

23/06/2015 - Developer Approval Received

24/06/2015 - Engineering Ordered

26/06/2015 - Developers Approval re-submitted due to change to render on façade

29/06/2015 - Developers Approval received

29/06/2015 - Formal Approval received by AFG Home Loans

30/06/2015 - Engineering received

07/07/2015 - Signed AFG loan documents

09/07/2015 - BOE application received back from South East Water

09/07/2015 - BOE application submitted to Casey Council

13/07/2015 - Final checks begun on file before application of Planning Permit

14/07/2015 - Plans finalised

23/07/2015 - Received BOE approval

24/07/2015 - Application for Building Permit submitted

29/07/2015 - Building Permit received

29/07/2015 - AFG Homes Loans settlement

05/08/2015 - Handed over to Construction

11/08/2015 - Site cut completed (a day earlier than scheduled)

14/08/2015 - Screw piles completed

21/08/2015 - Underground power installed

26/08/2015 - Drains and pipes completed

04/09/2015 - Slab prep completed

07/09/2015 - Slab poured

09/09/2015 - Framing Started

11/09/2015 - Framing complete - although a door is in the wrong place

14/09/2015 - Told by Site Supervisor retaining wall will be built "Next Week"

27/09/2015 - Windows in, roof on.  Rough-in started

27/09/2015 - Told by Site Supervisor (again) retaining wall will be built "Next Week"

08/10/2015 - Advised our SS is no longer with the company

21/10/2015 - OMG, new SS is now telling us retaining wall is another 2 weeks away as our bricks are now in the way......

22/10/2015 - After getting a bit p*ssed off at them, the bricklayers have been brought in early and started today

29/10/2015 - Told by Site Supervisor (again) retaining wall will be built either today or tomorrow.

30/10/2015 - Bricks finished and retaining walls built :)

03/11/2015 - Plaster walls in

13/11/2015 - Lock up stage completed

20/11/2015 - Fixing, render (unpainted), stormwater connection completed

27/11/2015 - All cabinetry is done

04/12/2015 - Render and all other painting 'completed'

11/12/2015 - Tiling started; garage door installed

18/12/2015 - Tiling nearly finished; floating floor installed, electrical completed

23/12/2015 - Tiling finished (a few repairs required), carpet nearly finished

13/01/2016 - Driveway poured, flyscreens, robe doors and mirrors installed.

22/01/2016 - New Home Presentation - couple of minor things to be fixed

29/01/2016 - 2nd Inspection - all good

03/02/2016 - GOT THE KEYS!!!