09/05/2014 - Signed Land Contract
28/06/2014 - Signed PWC to build St Tropez 28 with Boutique Homes
11/12/2014 - Colours appointment; discovered forged signatures
21/12/2014 - Signed Quotation to build Essex 27 with Porter Davis Homes
06/01/2015 - Cancelled PWC with Boutique Homes
06/01/2015 - Finalised quotation with Porter Davis Homes – File sent to Head Office
02/03/2015 - World of Style appointment with Porter Davis Homes
11/03/2015 - Land Titles issued
23/03/2015 - Tender appointment with Porter Davis Homes; site works a staggering $40k ($15k above what was originally quoted)
25/03/2015 - Land Settlement
28/03/2015 - Re-signed PWC to build St Tropez with Boutique Homes
30/03/2015 - Cancelled build with Porter Davis Homes
30/04/2015 - Pre-approval from Westpac received
08/05/2015 - Contract signing and electrical appointment with Boutique Homes
19/05/2015 - Westpac undervalued house/land by $34k
01/06/2015 - Colours selection
10/06/2015 - Build Over Easement (BOE) application submitted to South East Water
17/06/2015 - Developers Approval submitted
23/06/2015 - Developer Approval Received
24/06/2015 - Engineering Ordered
26/06/2015 - Developers Approval re-submitted due to change to render on façade
29/06/2015 - Developers Approval received
29/06/2015 - Formal Approval received by AFG Home Loans
30/06/2015 - Engineering received
07/07/2015 - Signed AFG loan documents
09/07/2015 - BOE application received back from South East Water
09/07/2015 - BOE application submitted to Casey Council
13/07/2015 - Final checks begun on file before application of Planning Permit
14/07/2015 - Plans finalised
23/07/2015 - Received BOE approval
24/07/2015 - Application for Building Permit submitted
29/07/2015 - Building Permit received
29/07/2015 - AFG Homes Loans settlement
05/08/2015 - Handed over to Construction
11/08/2015 - Site cut completed (a day earlier than scheduled)
14/08/2015 - Screw piles completed
21/08/2015 - Underground power installed
26/08/2015 - Drains and pipes completed
04/09/2015 - Slab prep completed
07/09/2015 - Slab poured
09/09/2015 - Framing Started
11/09/2015 - Framing complete - although a door is in the wrong place
14/09/2015 - Told by Site Supervisor retaining wall will be built "Next Week"
27/09/2015 - Windows in, roof on. Rough-in started
27/09/2015 - Told by Site Supervisor (again) retaining wall will be built "Next Week"
08/10/2015 - Advised our SS is no longer with the company
21/10/2015 - OMG, new SS is now telling us retaining wall is another 2 weeks away as our bricks are now in the way......
22/10/2015 - After getting a bit p*ssed off at them, the bricklayers have been brought in early and started today
29/10/2015 - Told by Site Supervisor (again) retaining wall will be built either today or tomorrow.
30/10/2015 - Bricks finished and retaining walls built :)
03/11/2015 - Plaster walls in
13/11/2015 - Lock up stage completed
20/11/2015 - Fixing, render (unpainted), stormwater connection completed
27/11/2015 - All cabinetry is done
04/12/2015 - Render and all other painting 'completed'
11/12/2015 - Tiling started; garage door installed
18/12/2015 - Tiling nearly finished; floating floor installed, electrical completed
23/12/2015 - Tiling finished (a few repairs required), carpet nearly finished
13/01/2016 - Driveway poured, flyscreens, robe doors and mirrors installed.
22/01/2016 - New Home Presentation - couple of minor things to be fixed
29/01/2016 - 2nd Inspection - all good
03/02/2016 - GOT THE KEYS!!!